1

Project Background

 

A provincial power company in Mexico is constructing a new 110 kV substation, with a large power engineering EPC contractor responsible for the project. The main components of the substation include a 110 kV main transformer, GIS switchgear, 110 kV power cables, current transformers, surge arresters, as well as relay protection and secondary control systems.

When the project entered the final acceptance phase, the owner required the on-site handover tests for major electrical equipment to be completed within 30 days, focusing on AC withstand voltage, partial discharge, surge arrester, grounding, and relay protection tests. All tests were required to be conducted on-site, with traceable test data that met the acceptance requirements of the owner, the supervising engineer, and third-party testing agencies.

 

The project implementation faced three main challenges:

First, the test objects were different.

Main transformers, GIS, cables, current transformers, and surge arresters have different test voltages, capacities, frequencies, and testing methods, requiring different test equipment configurations and settings for each test object.

Second, on-site testing conditions were limited.

Traditional power-frequency test equipment requires high power capacity and a large installation area. This makes on-site deployment more difficult. For capacitive loads such as main transformers, GIS, and long-distance cables, traditional power-frequency testing makes on-site testing more difficult.

Third, on-site electromagnetic interference significantly affects partial discharge measurements.

Live power lines and construction equipment around the substation create a complex electromagnetic environment. Reducing background noise and obtaining stable, repeatable partial discharge results are important for project acceptance.

After comparing the technical solutions, the client selected the solution provided by Wuhan Goldhome. It includes a partial discharge-free variable-frequency series resonance test system and supporting electrical test equipment.

 

2

Project Requirements and Technical Specifications

 

According to the project bidding documents, equipment technical agreements, and on-site testing requirements, the project shall comply with or refer to the following standards:

  • GB/T 16927.1 - High-Voltage Test Techniques
  • GB 50150 - Standard for Acceptance Tests of Electrical Equipment in Electrical Installation Projects
  • DL/T 596 - Procedures for Preventive Testing of Power Equipment
  • IEC 60270 - High-voltage test techniques – Partial discharge measurements
  • DL/T 849 Series - General Technical Conditions for High-Voltage Test Equipment
  • DL/T 995 - Procedures for the Inspection of Relay Protection and Power System Safety Automatic Devices

 

Tested Equipment

Main Test Items

Main Technical Requirements

110 kV Main Transformer

AC withstand voltage, partial discharge and related insulation tests

The test voltage and partial discharge limit shall comply with the technical agreement, manufacturer's requirements and applicable standards.

110 kV GIS

On-site AC withstand voltage and partial discharge

Comply with the project technical agreement and applicable standards.

110 kV Power Cable

AC withstand voltage

Test voltage, frequency and duration shall be determined according to the rated cable parameters and applicable standards.

CT / PT

Insulation, ratio, polarity, excitation characteristics, etc.

Comply with equipment technical documents and handover test requirements.

Metal-oxide Surge Arrester

DC 1mA reference voltage, leakage current, etc.

Comply with the manufacturer's requirements and applicable standards.

Earthing System

Earthing resistance, earthing continuity, etc.

Comply with project technical requirements and relevant standards.

Relay Protection System

Setting value verification, secondary injection, overall group test

Verify the correctness of protection logic, input-output signals and tripping circuits.

The total project duration is approximately 60 days. About 15 days are allocated to AC withstand voltage and partial discharge testing of primary equipment. Because multiple test objects are involved, equipment and personnel must be scheduled to allow parallel testing.

 

3

On-Site Survey and Analysis of Technical Issues

 

After arriving at the site, the Goldhome technical team surveyed the test area, power supply, equipment layout, grounding system, and electromagnetic environment.

The on-site test area is approximately 30 m × 15 m, so a large fixed test site cannot be built. The substation has limited power capacity and cannot easily meet the input power requirements of traditional high-capacity power-frequency test equipment. Therefore, the site requires a solution with low input power and high mobility.

Live power lines and construction equipment are also near the site, causing significant electromagnetic interference and increasing the requirements for partial discharge measurements.

The project site is located in the Mexican Plateau at an elevation of approximately 2,200 m. The high-altitude environment affects air insulation, equipment heat dissipation, and operating conditions. Therefore, equipment selection and test conditions must be checked for the site elevation.

image001

Based on the site conditions, the traditional power-frequency test transformer solution has the following limitations:

  • High testing power capacity requirements;
  • Significant workload associated with equipment transportation, hoisting, and on-site positioning;
  • Capacitive loads, such as long-distance cables, require a large testing capacity;
  • On-site partial discharge measurements are susceptible to external electromagnetic interference;
  • Large equipment hinders the rapid completion of test setup within limited space.

Therefore, this project uses variable-frequency series resonance technology as the main AC withstand voltage test solution. The resonance circuit compensates for the capacitive reactive power of the test object. This reduces the required test power capacity and makes on-site deployment easier.

 

4

Comprehensive Solution for Handover Testing at 110 kV Substations

 

4.1 Overall Solution Architecture

Goldhome designed an integrated on-site testing solution centered on the PD-Free Variable Frequency Series Resonance Test System.

The solution consists of a high-voltage testing system for primary equipment, a partial discharge measurement system, testing equipment for transformers and current/voltage transformers, surge arrester testing equipment, grounding testing equipment, and relay protection testing equipment.

The PD-Free Variable Frequency Series Resonance System is mainly used for on-site AC withstand voltage tests on main transformers, GIS, and 110 kV power cables. It can also work with a digital partial discharge measurement system for simultaneous AC withstand voltage and partial discharge testing.

Modular reactors and frequency conversion control allow the resonance point to be selected according to the capacitance, test voltage, and test frequency of each test object.

 

4.2 Product and Equipment Configuration

Recommended Product

Quantity

Main Purpose

PD-Free Variable Frequency Series Resonance Test System

1 Set

For AC withstand voltage tests of main transformer, GIS and power cables

Digital Partial Discharge Measurement System

1 Set

For partial discharge measurement of main transformer, GIS and power cables

PD-Free Test Transformer

1 Unit

Auxiliary AC withstand voltage test and low-background partial discharge test

Relay Protection Test Set

1 Unit

Protection setting value verification, secondary injection and overall group test

CT/PT Analyzer

1 Unit

Ratio, polarity, excitation characteristics and related tests

Insulation Resistance Tester

1 Unit

Insulation resistance test for main transformer, GIS, CT/PT and other equipment

Transformer Turns Ratio Tester

1 Unit

Main transformer turns ratio and vector group tests

Transformer Winding Resistance Tester

1 Unit

DC resistance test for main transformer windings

DC High Voltage Test Set

1 Unit

DC 1mA reference voltage and leakage current test for surge arresters

Grounding System Tester

1 Unit

Grounding resistance and grounding continuity test

image003-1
PD-Free Variable Frequency Series Resonance Test System
image005
Digital Partial Discharge Measurement System
image007
Relay Protection Test Set
image009
CT/PT Analyzer
image011
Insulation Resistance Tester
image013
Transformer Turns Ratio Tester

 

5

Selection of Core Equipment and Technical Advantages

 

5.1 Partial Discharge-Free Variable-Frequency Series Resonance Test System

The series resonance system uses a reactor to resonate with the capacitance of the test object. This compensates for capacitive reactive power and reduces the active power required from the variable-frequency power supply.

Compared with traditional power-frequency test transformer solutions, the variable-frequency series resonance system is suitable for field AC withstand voltage tests on capacitive test objects such as main transformers, GIS, and long-distance cables.

This project uses a modular design. Reactors can be combined according to the capacitance and test voltage of each test object, and the test frequency can be adjusted by the variable-frequency power supply.

For this project, the required test power capacity is lower than that of the original power-frequency solution. The solution also reduces equipment transportation and on-site deployment work.

 

5.2 Partial Discharge-Free Design and Partial Discharge Measurement

For GIS and main transformers with partial discharge requirements, the test system must provide stable high-voltage output and control system background noise and external interference.

This project incorporates:

• A partial discharge-free test power supply design;

• Input and output filtering;

• Shielding of the high-voltage test circuit;

• Proper grounding and equipotential bonding;

• Digital partial discharge measurement;

• Narrowband and digital interference suppression.

Before testing, the background partial discharge level is measured and recorded. After the test voltage is applied, the test results are compared with the background data to improve the reliability and repeatability of the partial discharge results.

Under the specified test conditions, the system provides a low partial discharge background level and a stable environment for on-site partial discharge testing.

 

5.3 CT/PT Test System

CT/PT testers are used to perform handover tests related to current and potential transformers, including:

Turns ratio testing;

Polarity testing;

Excitation characteristic testing;

Secondary winding-related testing;

DC resistance testing, etc.

Depending on the CT/PT model and project technical requirements, corresponding dielectric loss, insulation, and other specialized testing equipment can be further configured.

 

5.4 Relay Protection Test System

The relay protection tester provides multiphase current and voltage outputs and can be used for:

Verification of protection settings;

Inspection of current and voltage inputs;

Verification of protection logic;

Inspection of digital inputs/outputs;

Verification of secondary circuits;

Transmission tests for the complete system.

Scheduling secondary system tests in parallel with primary equipment high-voltage tests can reduce waiting time.

 

6

Project Implementation Process

 
 
The project is divided into four main phases.

Phase 1: On-site Preparation Completed:

Equipment delivery to the site;

Demarcation of the test area;

Confirmation of safety distances;

Inspection of the temporary grounding system;

Technical briefing on the test plan;

Inspection of equipment and instruments.

Phase 2: Equipment Deployment Completed:

Vehicle-mounted resonance system in place;

Connection of the test power supply;

Reactor assembly;

Connection of the high-voltage test circuit;

Grounding and equipotential bonding;

Installation of the partial discharge measurement system.

Phase 3: System Commissioning

Start with low-voltage or no-load checks, followed by:

Test circuit inspection;

Insulation testing;

No-load voltage ramp-up;

Confirmation of resonance frequency;

System background partial discharge testing;

Identification of on-site interference sources;

Calibration of the partial discharge measurement system.

Phase 4: Formal Handover Testing

According to the on-site test plan, conduct the required tests on the main transformer, GIS, cables, current transformers, surge arresters, and secondary protection systems.

Primary equipment and secondary system tests are scheduled in parallel when site conditions allow.

All test data is recorded electronically according to project requirements, and a test report is prepared.

image015

 

7

On-Site Issues and Remedial Measures

 

7.1 Equipment Operation in High-Altitude Environments

The project site is located at an altitude of approximately 2,200 m. Based on on-site environmental conditions, the insulation margin, heat dissipation conditions, and operating loads of the test equipment were verified.

During on-site testing, equipment operating times were reasonably scheduled, and continuous operating conditions were adjusted based on ambient temperature and equipment temperature rise to ensure stable operation under specified conditions.

 

7.2 On-Site Partial Discharge Background Interference

The initial on-site partial discharge background level was approximately 20 pC, with significant electromagnetic interference present.

The technical team reduced background interference through the following measures:

· Optimizing the test circuit layout;

· Enhancing shielding of high-voltage and measurement circuits;

· Optimizing grounding and equipotential bonding;

· Implementing power supply filtering;

· Utilizing digital partial discharge interference suppression;

These measures enabled the partial discharge results to meet the project acceptance requirements.

 

8

Project Implementation Results

 

Item

Estimated Condition of Original Scheme

Goldhome Solution

Total Test Cycle

Approx. 60 days

Approx. 18 days

On-site Equipment Deployment

Transportation and hoisting of multiple pieces of equipment

Vehicle-mounted rapid deployment

Test Power Supply Requirement

High

Significantly reduced by adopting series resonance technology

Partial Discharge Test Background Noise

Approx. 20 pC

Project requirements are satisfied after on-site treatment

Data Processing

Data collation after returning to substation

On-site electronic recording and report generation

Project Acceptance

Risk of re-work

Successful project acceptance on the first attempt

 

9

Client Feedback on the Project

 

"Space at the project site was limited, and there were live power lines and construction equipment in the vicinity, so we were initially concerned that the on-site withstand voltage and partial discharge tests might be disrupted. The Goldhome technical team completed the site survey and design ahead of schedule and was able to deploy the equipment quickly upon its arrival. The partial discharge test data was stable, the test reports were compiled in a timely manner, and the entire project was completed as planned."

- Electrical Manager, Mexico Project Department

The project demonstrates the application of partial discharge-free variable-frequency series resonance technology for AC withstand voltage and partial discharge testing at 110 kV substations.

Following the project, both parties held further technical discussions on expansion projects and preventive testing services.

 

10

Advantages of the Project Solution

 

1. Coverage of Multiple Types of Primary Equipment

Through a modular variable-frequency series resonance system, on-site AC withstand voltage tests can be performed on various capacitive loads-such as main transformers, GIS, and cables-based on the parameters of the test subject.

2. Low-Background Partial Discharge Testing

Through partial discharge-free design, filtering, shielding, optimized grounding, and digital anti-interference technology, stable testing conditions are provided for partial discharge testing of GIS and main transformers.

3. Rapid On-Site Deployment

The vehicle-mounted and modular design reduces the workload associated with transporting and hoisting large equipment, making it suitable for the limited space conditions at substation sites.

4. Coordinated Primary and Secondary Testing

Through the combination of a series resonance system, partial discharge measurement system, CT/PT test equipment, and relay protection test equipment, the system enables the coordinated implementation of tests on both primary equipment and secondary systems.

5. Traceable Test Data

Test data is recorded electronically, facilitating review by owners, supervisors, and third-party testing agencies, as well as project archiving.

 

11

Related Solutions

 

  • 220kV Substation Preventive Testing Solution
  • New Energy Step-up Substation Electrical Equipment Handover Testing Solution
  • GIS AC Withstand Voltage and Partial Discharge Testing Solution
  • 110 kV Power Cable AC Withstand Voltage Testing Solution
  • On-site Transformer AC Withstand Voltage and Partial Discharge Testing Solution
  • Partial Discharge Detection System
  • Variable Frequency Series Resonance Test System

 

Conclusion

For on-site acceptance testing at 110 kV substations, a single high-voltage test device often cannot cover all testing requirements for different primary equipment and secondary systems. A more suitable approach is to use a modular and scalable test system based on the requirements of main transformers, GIS, cables, CTs/PTs, surge arresters, grounding systems, and relay protection devices.

With the PD-Free Variable Frequency Series Resonance Test System at its core, Goldhome integrates partial discharge measurement, current transformer testing, routine transformer testing, surge arrester testing, grounding testing, and relay protection testing equipment. The system can be customized according to the test scope of different substation projects, providing on-site acceptance test solutions for EPC contractors, power companies, third-party testing agencies, and substation construction entities.