1

Project Background

 

A Singapore-based industrial and mining company is involved in the construction and electrical maintenance of overseas wind farm projects. The company needs to establish high-voltage testing capabilities for the field acceptance of wind farm collector cables and pad-mounted transformers. The main testing activities include collector cable commissioning tests, relevant high-voltage-side tests for pad-mounted transformers, and insulation condition checks before energization.

Under field conditions, conventional power-frequency AC withstand test equipment often has a large size, high transport requirements, and relatively high requirements for the available site power supply. For long wind farm collector cables, the cable itself presents a significant capacitive load. If conventional power-frequency AC testing is used directly, the test system needs to provide a relatively large reactive power capacity.

For this reason, the project uses a wind farm series resonance cable test system as the core equipment for on-site high-voltage testing of collector cables. The series resonance method reduces the required capacity of the test power supply while supporting field transportation, sectional testing, and rapid deployment.

It should be noted that Singapore's public power system operates at 50 Hz, with 230 V commonly used for single-phase supply and 400 V for three-phase supply. Therefore, the "230 V 50 Hz" condition in this project is mainly considered as an input power supply condition for the test equipment (small-capacitance or short-cable tests can use a direct connection where permitted; for large-capacitance and long-cable tests, the variable-frequency power supply is recommended to use a 400 V three-phase supply or a generator set when required). It is not the test voltage applied to the collector cable.

 

The main project requirements include:

  • Long wind farm collector cables create relatively high capacity requirements for conventional AC withstand test equipment;
  • Limited site space requires good equipment mobility and field deployment capability;
  • Different test objects, such as pad-mounted transformers with relatively small capacitance and cables with relatively large capacitance, require suitable impedance matching and system adjustment;
  • Singapore projects have relatively strict requirements for electrical safety management, requiring appropriate design of equipment input power, grounding, protection against incorrect operation, discharge, and safety interlocks.

 

2

Project Requirements and Technical Specifications

 

Based on the site requirements, Wuhan Goldhome follows a technical approach combining cable testing and series resonance testing. Because wind farm collector cables may have different voltage ratings, conductor sizes, lengths, and capacitance values, the final number of resonance reactors and the system capacity should be calculated according to the actual cable parameters rather than determined only by the 230 V input supply.

 

Item

Technical Requirement

Application

Wind farm collector cable and pad-mounted transformer testing

Main Test Objects

Medium-voltage collector cables and high-voltage-side equipment of pad-mounted transformers

Equipment Input

230 V / 50 Hz single-phase or 400 V / 50 Hz three-phase, depending on equipment capacity and site power conditions

Main Test Method

Variable-frequency series resonance AC withstand test

Testing Method

Single-cable or sectional cable testing on site

Equipment Requirements

Modular, portable, and suitable for field deployment

Test Objects

Cables, pad-mounted transformers, and related primary equipment

Site Requirements

Grounding, safety barriers, discharge, and safety interlocks

Reference Standards

IEC 60060 series, IEC 60502-2, IEC 60840, SS 638, SS 551

Project Objective

Support commissioning, acceptance, and pre-energization testing

 

For high-voltage testing, IEC 60060-1:2025 specifies general terminology and test requirements for dielectric tests involving AC, DC, and impulse voltages. IEC 60060-2:2025 covers high-voltage measuring systems and measurement uncertainty, while relevant field testing requirements should also be considered together with IEC 60060-3.

For collector cables within the 6 kV to 30 kV range, IEC 60502-2:2014+A1:2024 and its applicable corrigenda cover relevant requirements for power cables and accessories with extruded insulation. For example, for an 18/30 kV cable, if the project specification requires a test voltage of $2.5U_0$, the corresponding test voltage is 45 kV. The actual acceptance test voltage, test duration, and test procedure shall be determined according to the project specification, cable manufacturer's documentation, and applicable standards.

It should be emphasized that the actual acceptance voltage, test duration, and test procedure should be based on the cable manufacturer's technical documentation, project specifications, applicable local regulations, and relevant standards. Electrical installations and temporary power supplies on site should comply with applicable SS 638 requirements. The grounding system should be designed and implemented according to applicable SS 551, SS 638, and project safety requirements. For maintenance of relevant electrical equipment rated up to 22 kV, SS 538 may be referenced where applicable. Where temporary electrical installations are involved at construction sites, the applicable requirements of SS 650 should also be considered.

 

3

Site Survey and Technical Analysis

 

Technical personnel from Wuhan Goldhome Hipot Electrical Co., Ltd. conducted a comprehensive analysis based on the project requirements, including the test area, equipment transportation conditions, power supply, and test cable parameters.

Three main aspects were considered during the site survey.

First, the parameters of the test cable were reviewed. Wind farm collector circuits often have relatively long cable sections, and cable-to-ground capacitance increases with cable length. Therefore, during an AC withstand test, the required test capacity must be calculated according to cable length, conductor size, cable construction, and capacitance per unit length.

Second, the site power supply was evaluated. The basic power supply condition for the project is 230 V, 50 Hz. Because a series resonance system balances the inductive reactance of the reactor with the capacitive reactance of the test cable at resonance ($X_L = X_C$), a properly designed system can significantly reduce the requirement for large-capacity input power. For large-capacitance and long-cable tests, if 400 V three-phase power is available on site, a three-phase input configuration may provide a better match to the system power requirements.

Third, site space and transportation conditions were considered. Wind farm test locations may be distributed across different collector circuits and pad-mounted transformer locations. Large fixed test equipment can be difficult to transport between test points. Therefore, a modular and split-type series resonance system is more suitable for this type of field application.

image001

The main technical challenges include:

  • Increased test capacity caused by the capacitance of long cables;
  • Limited available site power;
  • Different impedance and test parameters for pad-mounted transformers and cables;
  • Distributed wind farm test points requiring efficient equipment transportation and fast connection.

 

 

4

Solution Design

 

4.1 Overall Solution

To address the high capacitance of wind farm collector cables, Wuhan Goldhome Hipot Electrical Co., Ltd. uses a series resonance test system consisting of a variable-frequency power supply with filtering, multi-tap excitation transformer, resonance reactors, integrated voltage divider and compensation capacitor, and control and measurement system.

During operation, the variable-frequency power supply provides an adjustable-frequency output to the excitation transformer. The built-in filter reduces high-frequency harmonic components generated by PWM switching. After voltage transformation through the multi-tap excitation transformer, the system forms a resonant circuit with the resonance reactors and the test cable. When the system reaches resonance, the required high AC test voltage can be generated with relatively low input power.

This method is particularly suitable for AC withstand testing of capacitive loads such as power cables. By adding or removing resonance reactor modules, the total inductance and resonance range can be adjusted according to different cable lengths and capacitance values.

For pad-mounted transformer testing, the test method is determined according to the transformer high-voltage-side rated voltage, insulation level, and project test requirements. Cable testing and transformer testing do not use one fixed set of parameters. The multi-tap excitation transformer can be switched between different output taps, such as 1.5 kV / 3 kV / 6 kV, while the integrated voltage divider and compensation capacitor can provide additional capacitance. This helps reduce the resonance frequency for small-capacitance test objects such as pad-mounted transformers and prevents the resonance frequency from exceeding the permitted operating frequency range of the system.

 

4.2 Product Configuration

Product

Model / Specification

Quantity

Main Application

Variable-Frequency Series Resonance Test System

HMCXZ Series, customized according to cable capacitance

1 set

AC withstand testing of wind farm collector cables and pad-mounted transformers

Variable-Frequency Power Supply

Matching system, with built-in low-pass filter

1 unit

Provides adjustable-frequency power and reduces high-frequency harmonic components in PWM output

Excitation Transformer

Matching system, multi-tap output

1 unit

Voltage transformation and output adjustment for different cable and transformer impedance conditions

Resonance Reactors

Modular configuration, individual units can be connected in series or parallel

2–N units

Forms the resonant circuit with the test cable and adjusts total inductance

Integrated Voltage Divider and Compensation Capacitor

Matching system

1 set

High-voltage measurement and monitoring, and additional resonance capacitance for small-capacitance test objects

Digital Partial Discharge Test System

Optional, used with a PD-free resonance reactor

1 set

Partial discharge testing according to project requirements, with a target PD level of $\le 5\text{pC}$ under specified test conditions

High-Voltage Damping Discharge Device

With current-limiting resistor and grounding copper cable

1 set

Safe damping discharge after testing to reduce residual charge and accidental electric shock risk

 

Variable-Frequency Series Resonance Test System

image007

Product details are available through the Goldhome product center.

 

4.3 Why Use a Series Resonance Test System?

First, it is suitable for capacitive cable loads.

Power cables are typical capacitive test objects. Conventional power-frequency AC test equipment needs to continuously provide relatively high reactive power. A series resonance system uses the reactor to compensate for the capacitive current of the test cable ($X_L = X_C$). The system operates close to the resonance point, where the overall circuit approaches a resistive condition, significantly reducing the capacity requirement on the test power supply.

 

Second, it is suitable for wind farm field testing.

Wind farm collector circuits often have distributed test points, requiring equipment to be moved between different locations. A modular series resonance system can be configured according to the test object, making transportation and installation easier.

 

Third, the 230 V 50 Hz / 400 V input conditions can be designed according to the site.

Singapore's electrical system operates at 50 Hz, with 230 V single-phase and 400 V three-phase supplies commonly used for electrical installations.

Therefore, when only a 230 V 50 Hz supply is available on site, the input power and starting requirements of the variable-frequency power supply must be checked during equipment selection. If the input power requirement is high for long-cable testing, a 400 V three-phase supply or generator set can be selected according to the specific equipment configuration.

 

Fourth, cable testing can be combined with insulation diagnostics.

If the project requires not only AC withstand testing but also further evaluation of cable insulation condition, a PD-free resonance reactor and coupling capacitor can be selected. This allows additional partial discharge and dielectric loss testing, extending the testing capability from simple withstand testing to withstand testing plus insulation condition assessment.

 

4.4 Main Solution Advantages

Cable-specific capacity matching:

The system capacity is calculated according to cable length, capacitance per unit length, and target test voltage to achieve more accurate equipment configuration.

Improved field mobility:

The split-type configuration facilitates transportation between multiple collector circuit test points in wind farms.

Relatively low input power requirement:

The series resonance principle provides reactive power compensation and can reduce the capacity pressure on the test power supply when the system is properly designed.

Expandable testing and protection functions:

Multi-tap excitation and integrated compensation support different test objects, including pad-mounted transformers. A damping discharge device supports safe discharge of long cables. Additional partial discharge testing and cable fault location equipment can also be integrated into a more complete wind farm cable testing solution.

 

4.5 Comparison with Conventional Power-Frequency AC Withstand Testing

Comparison Item

Conventional Power-Frequency AC Test

Series Resonance Test

Cable suitability

General

Well suited for capacitive cable loads

Capacitive load capability

High equipment capacity may be required

Resonant operation reduces input power requirements

Field mobility

Large-capacity equipment can be difficult to transport

Modular design facilitates transportation

Input power requirement

Usually higher

Can be reduced through system design; 230 V / 400 V options depend on configuration

Testing different cable lengths and transformers

Limited flexibility

Reactor combinations and excitation taps provide flexible adjustment

Fault and discharge behavior

Fault current depends on transformer capacity and protection configuration

Resonance is disturbed after a fault, causing the circuit current to normally decrease rapidly, with protection and safe discharge provided

Wind farm field suitability

Depends on equipment capacity

Well suited

 

The comparison above describes typical characteristics of the two technical approaches. Actual equipment weight, input power, and testing capability should be determined according to the specific equipment model and project parameters.

 

5

Implementation Process

 

The project implementation follows the process of site preparation → equipment deployment → parameter adjustment → formal testing → acceptance confirmation.

Stage 1: Site Preparation
 

 

Confirm the test area, power supply, grounding system, safety barriers, and safety distances. Check both ends of the test cable and ensure that the cable is reliably isolated from other energized equipment. The grounding system should comply with applicable SS 551, SS 638, and project safety requirements. Where temporary electrical installations are involved at a construction site, applicable SS 650 requirements should also be considered.

image009

02

Stage 2: Equipment Deployment

Transport the variable-frequency power supply, excitation transformer, resonance reactors, and integrated voltage divider to the test area. Select the appropriate reactor combination and excitation transformer tap according to cable length and capacitance.

03

Stage 3: Commissioning

Check the primary connections, secondary control circuits, grounding system, and protection interlocks. When using a 230 V 50 Hz or 400 V power supply, verify the actual input capacity and starting condition of the variable-frequency power supply. Perform a low-voltage frequency sweep to identify the resonance point.

04

Stage 4: Formal Testing

Gradually increase the test voltage according to the approved project test procedure. Monitor the test object and system operating parameters during the specified test voltage and duration.

05

Stage 5: Acceptance

After testing, safely discharge the test object using the high-voltage damping discharge device. Record the test voltage, frequency, current, test duration, and other relevant data, and prepare the test report.

 

 

6

Expected Results

 

This case is a solution configuration example for wind farm testing applications in industrial and mining environments. Actual acceptance data should be based on the field test report. The main expected results are as follows:

 

Evaluation Item

Existing Test Condition

Expected Result with the Proposed Solution

On-site cable withstand testing

Relies on external testing services

Establishes in-house field testing capability

Large-capacitance load testing

High power supply capacity may be required

Series resonance compensation reduces power supply pressure

Equipment transportation

Large equipment is difficult to transport

Modular split-type equipment facilitates field transportation

Multiple test points and transformer adaptability

Limited flexibility for small-capacitance transformer testing

Multi-tap excitation and compensation capacitance support multiple test objects

Test data and safety management

Manual records and potential risks during grounding and discharge

Digital data recording and damping discharge equipment support safer field operation

Further diagnostics

Mainly withstand testing

Partial discharge and other diagnostic tests can be added

 

For extruded-insulation power cables rated up to 30 kV, relevant requirements of IEC 60502-2 can be considered. For higher-voltage cable systems, the applicable standard should be selected according to the cable voltage rating. For example, IEC 60840:2020+A1:2023 applies to extruded-insulation power cable systems and accessories with rated voltages above 30 kV up to 150 kV (Um = 170 kV).

Therefore, project acceptance should not be based only on the maximum output voltage of the test equipment. Cable rated voltage, test type, test duration, environmental conditions, and project technical specifications should all be considered.

 

7

Customer Feedback and Project Summary

 

"We were particularly concerned about the site power supply and equipment transportation. Long-cable testing previously required relatively high test equipment capacity. With the series resonance solution, the equipment configuration can be adjusted according to the cable parameters, making field operation more convenient."

The main value of this project can be summarized in three areas. First, the equipment is selected according to the capacitive load characteristics of wind farm collector cables. Second, the input configuration is designed according to the 230 V 50 Hz and 400 V site power conditions in Singapore. Third, cable withstand testing is combined with pad-mounted transformer testing and optional insulation diagnostics to help industrial companies establish their own field high-voltage testing capability.

Depending on the actual wind farm project scale, the solution can be further expanded to include cable partial discharge testing, dielectric loss testing, cable fault location, and comprehensive pad-mounted transformer testing.

 

8

Frequently Asked Questions

Q: 1. How Do You Select A Wind Farm Series Resonance Cable Test System For A Singapore Wind Farm Project?

A: First, confirm the collector cable rated voltage, length, conductor size, capacitance per unit length, and target test voltage. Then calculate the total cable capacitance and required test capacity.
The site power supply should also be confirmed. Singapore uses a 50 Hz electrical system, with 230 V single-phase and 400 V three-phase supplies commonly used for electrical installations. For long-cable testing, the input power requirement of the variable-frequency power supply should be carefully calculated.
The final number of resonance reactors and system capacity should be determined according to the actual cable parameters rather than simply selecting equipment based on the project name.

Q: 2. Can A 230 V 50 Hz Resonance Tester Be Used For Wind Farm Collector Cable Withstand Testing?

A: Whether a 230 V / 50 Hz input can be used depends on the input specification, rated input power, and available site power capacity of the specific series resonance test system.
The 230 V / 50 Hz supply is an equipment input condition, not the test voltage applied to the cable. For small-capacitance or short-cable tests, a 230 V single-phase supply can be used when permitted by the equipment specification. For large-capacitance and long-cable testing, the required input current and power must be calculated. A 400 V three-phase supply or generator set may be required when the input power demand is high.
The series resonance system uses the variable-frequency power supply to control the excitation transformer and resonance circuit and then generates the required high-voltage test output. Therefore, equipment input voltage and high-voltage test output must be considered separately during equipment selection.

Q: 3. Which Standards Should Be Considered For High-Voltage Testing Of Wind Farm Collector Cables In Singapore?

A: The applicable standards depend on the cable rated voltage and project technical requirements.
Singapore electrical installations can refer to SS 638, while grounding can refer to SS 551. High-voltage testing can refer to the IEC 60060 series. For 6 kV to 30 kV extruded-insulation power cables, IEC 60502-2 can be considered. For cable systems above 30 kV up to 150 kV, IEC 60840 can be considered.
For maintenance of relevant electrical equipment rated up to 22 kV, SS 538 may be referenced where applicable. Where temporary electrical installations are involved at construction sites, applicable SS 650 requirements should also be considered.
The final test voltage and test procedure should always be determined according to the project specification, manufacturer's requirements, and applicable local regulations.

Q: 4. Why Is Series Resonance Commonly Used Instead Of Conventional Power-Frequency AC Testing For Wind Farm Collector Cables?

A: Power cables have significant capacitive characteristics, and capacitive current increases as cable length increases. Conventional power-frequency AC test equipment therefore needs sufficient capacity to continuously provide the required reactive power.
A series resonance system uses a reactor to form a resonant circuit with the cable ($X_L = X_C$). At the resonance point, the system operates with reduced reactive power demand from the input supply. This makes series resonance a suitable technical approach for long wind farm collector cables, especially where site power capacity is limited.

Q: 5. Can The Same Equipment Be Used For Wind Farm Pad-Mounted Transformer AC Hipot Testing And Collector Cable Testing?

A: The same series resonance system can be used for both applications when its voltage, current, frequency, and capacity ranges meet the requirements of both test objects.
Pad-mounted transformers and collector cables have different rated voltages, capacitance values, and test requirements. However, the system can be configured with a multi-tap excitation transformer, adjustable resonance reactor combinations, and compensation capacitors to match different test objects.
For small-capacitance test objects such as pad-mounted transformers, additional compensation capacitance can reduce the system resonance frequency and prevent the operating frequency from exceeding the permitted range.
Wuhan Goldhome Hipot Electrical Co., Ltd. can calculate the required test capacity separately according to the pad-mounted transformer and collector cable parameters and provide a customized system configuration.

9

Related Solutions

 

Related solutions include:

  • Wind Farm Collector Cable AC Withstand Test Solution
  • Wind Farm Pad-Mounted Transformer Commissioning Test Solution
  • Variable-Frequency Series Resonance Test System
  • Power Cable Partial Discharge Testing Solution
  • Medium-Voltage Cable AC Withstand and Insulation Diagnostic Solution

To select the appropriate equipment model, customers are recommended to provide the collector cable rated voltage, individual cable length, number of cores and conductor cross-section, capacitance per unit length, number of cables to be tested, and available 230 V / 400 V site power capacity.

Based on these parameters, Wuhan Goldhome Hipot Electrical Co., Ltd. can calculate the required number of resonance reactors and the appropriate system capacity.

Website: www.goldhomehipot.com

Service Hotline: +86 18971538425

WhatsApp:+86 18971538425